City audit finds project costs often ballooned over initial estimates


Highlights

Audit found 29% of the projects it reviewed had costs go at least 50 percent higher than original estimates.

Austin Public Works Department says it could conduct additional training on estimating the costs of projects.

Austin officials initially priced the Shoal Creek storm drain improvement project at about $1 million. But when the final bill was paid, the project actually cost Austin taxpayers about $7 million.

The renovations to City Hall and the City Council Chambers to make room for the larger, 11-member council that took office in 2015 was originally priced at $1.4 million. The costs soared to $6.4 million.

Those two projects were just a few in an audit of Austin’s Public Works Department released last week that found almost one-third — 29 percent — of the 48 projects it reviewed had costs balloon at least 50 percent higher than the staff’s original estimates.

“The City often did not prepare accurate project cost estimates or collect reliable data to do so,” the audit said.

ALSO READ: Your Austin tax dollars at work. Slowly, that is

The Public Works Department agreed with most of the findings in the audit and noted it could conduct additional training on estimating the costs of projects, and that the department has been making improvements since October 2016. It estimated full implementation of improvements by October 2018.

Public Works Director Richard Mendoza also noted in a memorandum responding to the audit that initial cost estimates are made with varying amounts of information about the project.

The audit of Austin’s capital project delivery was among the inquiries the city auditor’s office had scheduled for this year after previous audits, including one of the airport’s expansion, unearthed issues, according to a city spokesman.

Auditors reviewed a sample of projects and did not seek comprehensive data on the difference between initial cost estimates and final price tags for all capital improvement projects. Nor did auditors examine how these projects ballooned from the staff’s original cost considerations.

But the audit found flaws in the Austin Public Works Department’s quality control review process. In some cases, the department’s staff ignored the quality review process altogether, which sometimes led to change orders or increased project costs to fix issues that should have been identified earlier.

Of a sample of 48 projects, the audit found that 18 — 38 percent — were never submitted for review to the Public Works Department’s division that checks quality control. Those projects included a pedestrian bridge and the Turner Roberts Recreation Center.

ALSO RISING: How Waller Creek Tunnel costs topped $163 million

And of those sample projects that were submitted for review, that division failed to look over quality control plans for 39 percent of them.

In other cases, high-profile projects faced expedited or limited reviews.

For instance, management authorized staff to ignore comments made by the quality control division about the designs for the new Central Library.

“As a result, staff submitted designs for bid and construction without subjecting them to the full quality management process,” the audit said.

The library project saw its costs grow from $90 million to $125 million as its opening was delayed repeatedly. It is set to open Oct. 28, nearly a year after the original target date.

In another unspecified case, a project manager successfully convinced management to forgo quality management inspections because it would create “burdensome” delays, the audit said.

VISIT VOTETRACKER: See how your Austin City Council member voted on key issues

The Public Works Department appears to have improved its review process in recent years, but the audit still found a substantial number of projects did not undergo the full quality review process, which includes three reviews of designs along with the quality control plan.

In the new Central Library’s case, the auditors found that two oversights in the design phase led to about a $32,000 cost increase.

For instance, city had to fork over $14,557 more for the library project after a contractor discovered that design documents did not provide a power supply for portions of the library’s fire protection system.

“Many of the change estimates (and accompanying cost increases) we reviewed for the New Central Library stemmed from missing, unclear or conflicting items in the New Central Library designs that a quality review may have caught,” the audit states.

RELATED: Austin’s new Central Library opening delayed — again — to late this year

In every case auditors reviewed, the Public Works Department also allowed contractors to begin performing unauthorized work before those change orders were approved. For example, contractors performed $66,500 of work in 2015 on an erosion control wall for the Waller Creek Tunnel without approval. This happened five months after the Public Works Department had assured the City Council that it would follow the change order process, the audit said.

The audit also questioned the autonomy of project managers, who can approve new work with little oversight. In one unspecified project, a program manager agreed to allow $82,653 of steel work for the Central Library to be performed despite the manager believing the city was not getting a fair price. The manager ultimately agreed because he thought it would be better to accept the costs than face further delays in the beleaguered project.

The city has little it can do to recoup costs and could face litigation if the Public Works Department backed out on paying for the contractor’s completed work, the audit said.

In response to the audit, the Public Works Department’s staff said they would implement a leaner quality management process and streamline the change order process with the input from an already existing city staff team.



Reader Comments ...


Next Up in Local

Texas special education chief fired after questioning no-bid contract
Texas special education chief fired after questioning no-bid contract

The state’s new director of special education was fired Wednesday, one day after she filed a federal complaint claiming the Texas Education Agency wrongly entered into a $4.4 million, no-bid contract with a Georgia company to analyze private records for children with disabilities. Laurie Kash asked the U.S. Department of Education’s Office...
Don’t forget safety while shopping on Black Friday, police say
Don’t forget safety while shopping on Black Friday, police say

Holiday shopping mania can make it easy to forget some common-sense rules to keep you and your belongings safe. Austin and Sunset Valley police recommend these tips before hitting the stores on Black Friday: 1. Remove valuables from view: After a successful shopping run, you should place and secure all holiday packages in your trunk, away from prying...
Federal judge tosses out Texas abortion law
Federal judge tosses out Texas abortion law

For the third time this year, a federal judge has tossed out an abortion-related regulation in Texas — this time a law that bans a common type of second-trimester abortion unless doctors first employ an added procedure to ensure fetal demise. In a ruling issued Wednesday afternoon, U.S. District Judge Lee Yeakel of Austin said the law requires...
3 semis crash in Northeast Austin, cause closure on I-35

NORTHEAST AUSTIN 3 semis crash, cause closure on I-35 Three semis were involved in a collision in Northeast Austin on Wednesday, forcing authorities to briefly shut down the southbound lanes of Interstate 35 near the U.S. 290 interchange north of 51st Street on one of the busiest road travel days of the year. Diesel fuel spilled onto the roadway after...
Surprised by Austin SWAT near your home? It’s for safety, police say
Surprised by Austin SWAT near your home? It’s for safety, police say

When Austin police SWAT officers deploy, they can look intimidating. Team members wear beefed-up ballistic vests and armor, and they carry specialized weapons beyond what patrol officers typically carry. They roll into neighborhoods in armored vehicles, surround houses and block off streets, often prompting confused neighbors to call the media or seek...
More Stories